Sl. No. | Name of Dam / Reservoir | District | MWL (metre) | FRL (metre) | Spillway Crest Level (metre) | Live Storage at FRL (MCM) | Rule level (metre) | Blue level (metre) | Orange level (metre) | Red Level (metre) | Today’s Water level (metre) | Today’s Live Storage (MCM) | % Storage wrt Live Storage at FRL | Same day previous year Water level (metre) | Same day previous year Live Storage (MCM) | Inflow (cumecs) | Power House Discharge(cumecs) | Spillway release (cumecs) | Total Outflow (cumecs) | Rain fall (mm) | Remarks |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20=18+19 | 21 | 22 |
1 | IDUKKI | IDK | 2408.5 ft | 2403 ft | 2373 ft | 1459.49 | 2386.81 ft | 2378.81 | 2384.81 | 2385.81 | 2332.44ft | 465.736 | 31.91% | 2386.74ft | 1187.750 | 22.80 | 26.30 | 0.00 | 26.30 | 0.40 | |
2 | IDAMALAYAR | EKM | 171.00 | 169.00 | 161.00 | 1017.80 | 163.50 | 162.00 | 162.50 | 163.00 | 145.91 | 426.110 | 41.87% | 163.76 | 866.612 | 19.57 | 11.76 | 0.00 | 11.76 | 0.00 | |
3 | KAKKI (ANATHODE ) | PTTA | 982.160 | 981.460 | 975.360 | 446.51 | 976.00 | 974.00 | 975.00 | 975.50 | 957.76 | 163.980 | 36.72% | 976.19 | 360.460 | 15.59 | 15.59 | 0.00 | 15.59 | 2.00 | |
4 | BANASURASAGAR (K A SCHEME) | WND | 775.600 | 775.600 | 767.000 | 201.00 | 774.50 | 773.00 | 773.50 | 774.00 | 768.85 | 122.550 | 60.97% | 774.60 | 188.350 | 4.63 | 0.00 | 0.00 | 0.00 | 0.00 | Tunnel Outflow – 0.0 MCM |
5 | SHOLAYAR | TSR | 2663 ft | 2663 ft | 2642 ft | 149.09 | 2658.00 | 2659.50 | 2661.00 | 2639.10ft | 91.300 | 61.24% | 2660.10 | 140.903 | 15.50 | 3.69 | 0.00 | 3.69 | 0.00 | ||
6 | MADUPETTY | IDK | 1599.59 | 1599.59 | 1594.71 | 54.77 | 1596.00 | 1597.00 | 1598.00 | 1588.45 | 28.240 | 51.56% | 1597.60 | 48.940 | 2.31 | 0.00 | 0.00 | 0.00 | 0.00 | Sluice discharge/day – 0.00 McM | |
7 | ANAYIRANKAL | IDK | 1210.070 | 1207.020 | 1207.020 | 49.83 | 1205.02 | 1206.02 | 1207.02 | 1196.89 | 13.3128 | 26.72% | 1204.91 | 40.594 | 0.80 | 0.00 | 0.00 | 0.00 | 0.00 | Sluice discharge/day – 0 McM | |
8 | PONMUDI | IDK | 708.660 | 707.750 | 701.350 | 47.40 | 704.50 | 705.50 | 706.50 | 697.65 | 26.3557 | 55.60% | 706.60 | 44.197 | 9.13 | 6.35 | 0.00 | 6.35 | 0.00 | ||
9 | KUTTIYADI (KAKKAYAM) | KKD | 758.040 | 758.040 | 751.640 | 33.98 | 755.50 | 756.50 | 757.50 | 748.29 | 12.610 | 37.11% | 757.76 | 33.30 | 3.25 | 10.34 | 0.00 | 10.34 | 3.00 | ||
10 | PAMBA | PTTA | 986.330 | 986.330 | 981.460 | 31.15 | 982.00 | 983.50 | 984.50 | 964.20 | 0.77 | 2.47% | 981.20 | 21.48 | 6.92 | 0.00 | 0.00 | 0.00 | 4.00 | ||
11 | PORINGALKUTHU | TSR | 423.980 | 423.980 | 419.410 | 30.30 | 421.00 | 422.00 | 423.00 | 419.45 | 18.38 | 60.66% | 420.20 | 20.250 | 25.55 | 31.33 | 0.00 | 31.33 | 0.00 | ||
12 | KUNDALA | IDK | 1759.30 | 1758.690 | 7.65 | 1755.00 | 1756.00 | 1757.00 | 1754.70 | 4.850 | 63.40% | 1758.20 | 7.045 | 0.58 | 0.00 | 0.00 | 0.00 | 7.40 | Sluice discharge/day – 0 McM | ||
13 | KALLARKUTTY | IDK | 456.900 | 456.590 | 450.200 | 6.43 | 455.00 | 452.75 | 4.091 | 63.62% | 456.30 | 6.281 | 15.63 | 14.15 | 0.00 | 14.15 | 0.00 | ||||
14 | ERATTAYAR | IDK | 754.380 | 754.380 | 748.280 | 5.29 | 748.28 | 746.80 | 0.8590 | 16.23% | 747.70 | 0.00 | |||||||||
15 | LOWER PERIYAR | IDK | 256.00 | 253.00 | 237.74 | 4.55 | 252.00 | 249.30 | 3.017 | 66.31% | 253.00 | 4.550 | 25.92 | 25.92 | 0.00 | 25.92 | 0.00 | ||||
16 | MOOZHIYAR | PTTA | 192.940 | 192.630 | 186.530 | 1.16 | 190.00 | 187.05 | 0.472 | 40.69% | 185.60 | 0.327 | 10.85 | 13.66 | 0.00 | 13.66 | 0.00 | ||||
17 | KALLAR | IDK | 824.480 | 824.480 | 818.380 | 0.76 | 823.50 | 820.10 | 0.1880 | 24.64% | 820.40 | 0.00 | |||||||||
18 | SENGULAM (PUMPING STORAGE DAM) | IDK | 849.49 | 847.640 | 847.64 | 0.39 | 846.45 | 0.106 | 27.18% | 846.10 | 0.024 | 5.25 | 6.07 | 0.00 | 6.07 | 0.00 |