Sl. No. | Name of Dam / Reservoir | District | MWL (metre) | FRL (metre) | Spillway Crest Level (metre) | Live Storage at FRL (MCM) | Rule level (metre) | Blue level (metre) | Orange level (metre) | Red Level (metre) | Today’s Water level (metre) | Today’s Live Storage (MCM) | % Storage wrt Live Storage at FRL | Same day previous year Water level (metre) | Same day previous year Live Storage (MCM) | Inflow (cumecs) | Power House Discharge(cumecs) | Spillway release (cumecs) | Total Outflow (cumecs) | Rain fall (mm) | Remarks |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20=18+19 | 21 | 22 |
1 | IDUKKI | IDK | 2408.5 ft | 2403 ft | 2373 ft | 1459.49 | 2397.78 ft | 2389.78 | 2395.78 | 2396.78 | 2347.40ft | 637.389 | 43.67% | 2384.56ft | 1151.662 | 50.02 | 22.80 | 0.00 | 22.80 | 3.20 | |
2 | IDAMALAYAR | EKM | 171.00 | 169.00 | 161.00 | 1017.80 | 166.60 | 165.10 | 165.60 | 166.10 | 153.36 | 593.338 | 58.30% | 162.74 | 837.390 | 40.58 | 26.38 | 0.00 | 26.38 | 25.60 | |
3 | KAKKI (ANATHODE ) | PTTA | 982.160 | 981.460 | 975.360 | 446.51 | 977.95 | 975.95 | 976.95 | 977.45 | 971.47 | 297.730 | 66.68% | 975.02 | 344.080 | 43.28 | 27.30 | 0.00 | 27.30 | 19.00 | |
4 | BANASURASAGAR (K A SCHEME) | WND | 775.600 | 775.600 | 767.000 | 201.00 | 775.00 | 773.50 | 774.00 | 774.50 | 772.30 | 161.350 | 80.27% | 773.25 | 172.350 | 6.94 | 0.00 | 0.00 | 0.00 | 0.00 | Tunnel Outflow -0.00 MCM |
5 | SHOLAYAR | TSR | 2663 ft | 2663 ft | 2642 ft | 149.09 | 2658.00 | 2660.00 | 2661.00 | 2660.80ft | 142.870 | 95.83% | 2659.50 | 139.260 | 8.42 | 14.91 | 0.00 | 14.91 | 0.00 | ||
6 | MADUPETTY | IDK | 1599.59 | 1599.59 | 1594.71 | 54.77 | 1596.00 | 1597.00 | 1598.00 | 1592.50 | 36.340 | 66.35% | 1596.65 | 46.565 | 2.31 | 0.00 | 0.00 | 0.00 | 5.60 | Sluice discharge/day – 0.00 McM | |
7 | ANAYIRANKAL | IDK | 1210.070 | 1207.020 | 1207.020 | 49.83 | 1205.02 | 1206.02 | 1207.02 | 1199.90 | 22.5936 | 45.34% | 1207.08 | 50.147 | 3.32 | 0.00 | 0.00 | 0.00 | 35.00 | Sluice discharge/day – 0 McM | |
8 | PONMUDI | IDK | 708.660 | 707.750 | 701.350 | 47.40 | 704.50 | 705.50 | 706.50 | 704.20 | 38.5652 | 81.36% | 705.85 | 42.393 | 16.87 | 16.87 | 0.00 | 16.87 | 9.00 | ||
9 | KUTTIYADI (KAKKAYAM) | KKD | 758.040 | 758.040 | 751.640 | 33.98 | 755.50 | 756.50 | 757.50 | 750.69 | 17.170 | 50.53% | 751.85 | 19.49 | 7.06 | 15.51 | 0.00 | 15.51 | 12.00 | ||
10 | PAMBA | PTTA | 986.330 | 986.330 | 981.460 | 31.15 | 982.00 | 983.50 | 984.50 | 972.40 | 8.78 | 28.19% | 975.25 | 12.51 | 11.41 | 0.00 | 0.00 | 0.00 | 22.00 | ||
11 | PORINGALKUTHU | TSR | 423.980 | 423.980 | 419.410 | 30.30 | 421.00 | 422.00 | 423.00 | 420.15 | 20.12 | 66.40% | 417.00 | 13.10 | 33.10 | 53.35 | 0.00 | 53.35 | 0.00 | ||
12 | KUNDALA | IDK | 1759.30 | 1758.690 | 7.65 | 1755.00 | 1756.00 | 1757.00 | 1758.35 | 7.160 | 93.59% | 1758.05 | 6.935 | 3.01 | 0.00 | 3.47 | 3.47 | 2.00 | Sluice discharge/day – 0 McM | ||
13 | KALLARKUTTY | IDK | 456.900 | 456.590 | 450.200 | 6.43 | 455.00 | 453.00 | 4.219 | 65.61% | 452.50 | 3.964 | 36.44 | 30.23 | 0.00 | 30.23 | 0.00 | ||||
14 | ERATTAYAR | IDK | 754.380 | 754.380 | 748.280 | 5.29 | 748.28 | 747.00 | 0.9365 | 17.70% | 746.90 | 0.00 | |||||||||
15 | LOWER PERIYAR | IDK | 256.00 | 253.00 | 237.74 | 4.55 | 252.00 | 248.40 | 2.666 | 58.59% | 250.60 | 3.536 | 41.09 | 45.60 | 0.00 | 45.60 | 0.00 | ||||
16 | MOOZHIYAR | PTTA | 192.940 | 192.630 | 186.530 | 1.16 | 190.00 | 188.00 | 0.569 | 49.05% | 186.50 | 0.415 | 24.33 | 22.46 | 0.00 | 22.46 | 0.00 | ||||
17 | KALLAR | IDK | 824.480 | 824.480 | 818.380 | 0.76 | 823.50 | 820.20 | 0.1917 | 25.12% | 820.20 | 0.00 | |||||||||
18 | SENGULAM (PUMPING STORAGE DAM) | IDK | 849.49 | 847.640 | 847.64 | 0.39 | 846.65 | 0.154 | 39.49% | 846.80 | 0.189 | 10.09 | 9.68 | 0.00 | 9.68 | 5.60 |