Sl. No. | Name of Dam / Reservoir | District | MWL (metre) | FRL (metre) | Spillway Crest Level (metre) | Live Storage at FRL (MCM) | Rule level (metre) | Blue level (metre) | Orange level (metre) | Red Level (metre) | Today’s Water level (metre) | Today’s Live Storage (MCM) | % Storage wrt Live Storage at FRL | Same day previous year Water level (metre) | Same day previous year Live Storage (MCM) | Inflow (cumecs) | Power House Discharge(cumecs) | Spillway release (cumecs) | Total Outflow (cumecs) | Rain fall (mm) | Remarks |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20=18+19 | 21 | 22 |
1 | IDUKKI | IDK | 2408.5 ft | 2403 ft | 2373 ft | 1459.49 | 2400.03 ft | 2392.03 | 2398.03 | 2399.03 | 2362.98ft | 834.468 | 57.18% | 2382.70ft | 1120.869 | 49.42 | 8.34 | 0.00 | 8.34 | 18.00 | |
2 | IDAMALAYAR | EKM | 171.00 | 169.00 | 161.00 | 1017.80 | 168.50 | 167.00 | 167.50 | 168.00 | 158.29 | 712.830 | 70.04% | 160.37 | 712.830 | 13.30 | 0.00 | 0.00 | 0.00 | 0.00 | |
3 | KAKKI (ANATHODE ) | PTTA | 982.160 | 981.460 | 975.360 | 446.51 | 981.00 | 979.00 | 980.00 | 980.50 | 975.93 | 356.820 | 79.91% | 976.06 | 358.640 | 26.38 | 8.56 | 0.00 | 8.56 | 42.00 | |
4 | BANASURASAGAR (K A SCHEME) | WND | 775.600 | 775.600 | 767.000 | 201.00 | 775.60 | 774.10 | 774.60 | 775.10 | 771.50 | 151.950 | 75.60% | 771.10 | 147.750 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Tunnel Outflow – 0.00 MCM |
5 | SHOLAYAR | TSR | 2663 ft | 2663 ft | 2642 ft | 149.09 | 2658.00 | 2660.00 | 2661.00 | 2659.70ft | 139.810 | 93.78% | 2660.00 | 140.620 | 17.54 | 14.40 | 0.00 | 14.40 | 0.00 | ||
6 | MADUPETTY | IDK | 1599.59 | 1599.59 | 1594.71 | 54.77 | 1596.00 | 1597.00 | 1598.00 | 1595.55 | 43.690 | 79.77% | 1599.00 | 52.940 | 2.18 | 0.74 | 0.00 | 0.74 | 0.00 | Sluice discharge/day – 0.00 McM | |
7 | ANAYIRANKAL | IDK | 1210.070 | 1207.020 | 1207.020 | 49.83 | 1205.02 | 1206.02 | 1207.02 | 1206.24 | 46.4205 | 93.16% | 1207.14 | 50.456 | 1.01 | 0.00 | 0.00 | 0.00 | 5.00 | Sluice discharge/day – 0 McM | |
8 | PONMUDI | IDK | 708.660 | 707.750 | 701.350 | 47.40 | 704.50 | 705.50 | 706.50 | 706.15 | 43.0885 | 90.90% | 705.10 | 40.653 | 17.65 | 20.33 | 0.00 | 20.33 | 5.00 | ||
9 | KUTTIYADI (KAKKAYAM) | KKD | 758.040 | 758.040 | 751.640 | 33.98 | 755.50 | 756.50 | 757.50 | 754.38 | 24.840 | 73.10% | 753.07 | 21.93 | 1.39 | 6.67 | 0.00 | 6.67 | 0.00 | ||
10 | PAMBA | PTTA | 986.330 | 986.330 | 981.460 | 31.15 | 982.00 | 983.50 | 984.50 | 976.00 | 13.63 | 43.76% | 976.15 | 13.86 | 5.10 | 0.00 | 0.00 | 0.00 | 0.00 | ||
11 | PORINGALKUTHU | TSR | 423.980 | 423.980 | 419.410 | 30.30 | 421.00 | 422.00 | 423.00 | 422.20 | 25.25 | 83.33% | 415.90 | 10.94 | 13.58 | 12.13 | 0.00 | 12.13 | 0.00 | ||
12 | KUNDALA | IDK | 1759.30 | 1758.690 | 7.65 | 1755.00 | 1756.00 | 1757.00 | 1758.20 | 7.045 | 92.09% | 1758.05 | 6.935 | 2.31 | 0.00 | 2.31 | 2.31 | 0.00 | Sluice discharge/day – 0 McM | ||
13 | KALLARKUTTY | IDK | 456.900 | 456.590 | 450.200 | 6.43 | 455.00 | 453.15 | 4.296 | 66.81% | 453.00 | 4.219 | 26.37 | 26.66 | 0.00 | 26.66 | 0.00 | ||||
14 | ERATTAYAR | IDK | 754.380 | 754.380 | 748.280 | 5.29 | 748.28 | 747.20 | 1.0140 | 19.16% | 746.90 | 0.00 | |||||||||
15 | LOWER PERIYAR | IDK | 256.00 | 253.00 | 237.74 | 4.55 | 252.00 | 249.10 | 2.939 | 64.59% | 246.50 | 2.050 | 53.28 | 48.32 | 0.00 | 48.32 | 0.00 | ||||
16 | MOOZHIYAR | PTTA | 192.940 | 192.630 | 186.530 | 1.16 | 190.00 | 185.70 | 0.336 | 28.97% | 186.40 | 0.405 | 9.74 | 10.44 | 0.00 | 10.44 | 27.00 | ||||
17 | KALLAR | IDK | 824.480 | 824.480 | 818.380 | 0.76 | 823.50 | 820.40 | 0.1993 | 26.12% | 820.30 | ||||||||||
18 | SENGULAM (PUMPING STORAGE DAM) | IDK | 849.49 | 847.640 | 847.64 | 0.39 | 846.50 | 0.118 | 30.26% | 845.35 | shut down | 5.25 | 5.66 | 0.00 | 5.66 | 0.00 |