Sl. No. | Name of Dam / Reservoir | District | MWL (metre) | FRL (metre) | Spillway Crest Level (metre) | Live Storage at FRL (MCM) | Rule level (metre) | Blue level (metre) | Orange level (metre) | Red Level (metre) | Today’s Water level (metre) | Today’s Live Storage (MCM) | % Storage w.r.t Live Storage at FRL | Same day previous year Water level (metre) | Same day previous year Live Storage (MCM) | Inflow (cumecs) | Power House Discharge(cumecs) | Spillway release (cumecs) | Total Outflow (cumecs) | Rain fall (mm) | Remarks |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 17 | 18 | 19 | 20 | 21 | 22=20+21 | 23 | 24 |
1 | IDUKKI | IDK | 2408.5 ft | 2403 ft | 2373 ft | 1459.49 | 2377.95 ft | 2369.95 | 2375.95 | 2376.95 | 2341.12ft | 560.251 | 38.39% | 2322.54ft | 359.995 | 125.89 | 56.25 | 0.00 | 56.25 | 27.80 | |
2 | IDAMALAYAR | EKM | 171.00 | 169.00 | 161.00 | 1017.80 | 161.75 | 160.25 | 160.75 | 161.25 | 142.86 | 364.541 | 35.82% | 139.93 | 307.67 | 89.87 | 31.43 | 0.00 | 31.43 | 31.80 | |
3 | KAKKI (ANATHODE ) | PTTA | 982.160 | 981.460 | 975.360 | 446.51 | 975.36 | 973.36 | 974.36 | 974.86 | 955.52 | 146.750 | 32.87% | 953.41 | 131.970 | 54.35 | 30.97 | 0.00 | 30.97 | 27.00 | |
4 | BANASURASAGAR (K A SCHEME) | WND | 775.600 | 775.600 | 767.000 | 201.00 | 773.50 | 772.00 | 772.50 | 773.00 | 764.30 | 78.750 | 39.18% | 760.60 | 48.950 | 46.30 | 0.00 | 0.00 | 0.00 | 56.60 | Tunnel Outflow -0.00MCM (0.00 Cumecs) |
5 | SHOLAYAR | TSR | 2663 ft | 2663 ft | 2642 ft | 149.09 | 2658.00 | 2660.00 | 2661.00 | 2606.10ft | 37.620 | 25.23% | 2626.80ft | 68.320 | 22.73 | 3.98 | 0.00 | 3.98 | 41.20 | ||
6 | MADUPETTY | IDK | 1599.59 | 1599.59 | 1594.71 | 54.77 | 1596.00 | 1597.00 | 1598.00 | 1593.10 | 37.690 | 68.82% | 1585.50 | 22.540 | 1.45 | 0.00 | 0.00 | 0.00 | 37.00 | Sluice discharge/day -0 McM | |
7 | ANAYIRANKAL | IDK | 1210.070 | 1207.020 | 1207.020 | 49.83 | 1205.02 | 1206.02 | 1207.02 | 1192.22 | 5.2134 | 10.46% | 1195.37 | 10.6766 | 1.81 | 0.00 | 0.00 | 0.00 | 18.00 | Sluice discharge/day – 0 McM | |
8 | PONMUDI | IDK | 708.660 | 707.750 | 701.350 | 47.40 | 704.50 | 705.50 | 706.50 | 691.55 | 16.4201 | 34.64% | 696.55 | 24.5996 | 20.40 | 10.35 | 0.00 | 10.35 | 26.00 | ||
9 | KUTTIYADI (KAKKAYAM) | KKD | 758.040 | 758.040 | 751.640 | 33.98 | 755.50 | 756.50 | 757.50 | 749.20 | 14.200 | 41.79% | 750.11 | 16.010 | 27.62 | 15.15 | 0.00 | 15.15 | 52.00 | ||
10 | PAMBA | PTTA | 986.330 | 986.330 | 981.460 | 31.15 | 982.00 | 983.50 | 984.50 | 965.95 | 2.17 | 6.97% | 965.10 | 1.49 | 34.33 | 0.00 | 0.00 | 0.00 | 58.00 | ||
11 | PORINGALKUTHU | TSR | 423.980 | 423.980 | 419.410 | 30.30 | 421.00 | 422.00 | 423.00 | 419.55 | 18.63 | 61.49% | 419.20 | 17.75 | 56.88 | 45.31 | 0.00 | 45.31 | 49.00 | Vachumaram- 0.00 Mcm. | |
12 | KUNDALA | IDK | 1759.30 | 1758.690 | 7.65 | 1755.00 | 1756.00 | 1757.00 | 1743.50 | 0.575 | 7.52% | 1751.45 | 3.260 | 0.87 | 0.00 | 0.00 | 0.00 | 18.80 | Sluice discharge/day – 0 | ||
13 | KALLARKUTTY | IDK | 456.900 | 456.590 | 450.200 | 6.43 | 455.00 | 453.35 | 4.411 | 68.60% | 452.40 | 3.913 | 32.14 | 34.34 | 0.00 | 34.34 | 27.00 | ||||
14 | ERATTAYAR | IDK | 754.380 | 754.380 | 748.280 | 5.29 | 748.28 | 747.10 | 0.9752 | 18.43% | 746.90 | 0.9365 | 0.00 | ||||||||
15 | LOWER PERIYAR | IDK | 256.00 | 253.00 | 237.74 | 4.55 | 252.00 | 248.10 | 2.549 | 56.02% | 249.50 | 3.095 | 63.39 | 59.35 | 0.00 | 59.35 | 26.00 | ||||
16 | MOOZHIYAR | PTTA | 192.940 | 192.630 | 186.530 | 1.16 | 190.00 | 189.00 | 0.682 | 58.79% | 185.50 | 0.372 | 29.86 | 29.41 | 0.00 | 29.41 | 13.00 | Gate No 2 closed at 3 p.m..on 05.07.24 | |||
17 | KALLAR | IDK | 824.480 | 824.480 | 818.380 | 0.76 | 823.50 | 820.40 | 0.1993 | 26.12% | 820.10 | 0.1880 | |||||||||
18 | SENGULAM (PUMPING STORAGE DAM) | IDK | 849.49 | 847.640 | 847.64 | 0.39 | 846.65 | 0.154 | 39.49% | 846.65 | 0.154 | 8.34 | 7.66 | 0.00 | 7.66 | 11.00 |